Blog

06/12/2016

Six months on …

Today marks exactly six months since I joined Don Catchment Rivers Trust. It feels like only yesterday that […]
25/10/2016

Three down, two to go!

Bailey Construction have completed the first of the Larinier fish passes which is located at Steelbank weir. The […]
06/10/2016

Lady’s Bridge

  As mentioned on our last blog, the work at Lady’s Bridge weir to install an easement to […]
28/09/2016

One down, four to go!

The first of our five fish passage solutions has been completed at Lady’s Bridge near the Wicker in […]
14/09/2016

It’s all about the water!

At Brightside weir it’s all about water management!  The sandbags that were in place to dam the weir […]
30/08/2016

Moving on

Here’s more pictures of progress at Steelbank weir.  The concrete base has now been poured for the two […]